Wynn Al Marjan Island is reshaping the UAE skyline

The 70-floor Ras Al Khaimah tower has completed structural concrete work, with fit-outs underway across 1,504 rooms and suites.

Wynn Resorts and Marjan announced a construction milestone for Wynn Al Marjan Island in Ras Al Khaimah as the project reached topping out. The 70-floor tower has risen to 283 metres, achieving its highest structural concrete point 27 months after foundation works began. With the spire installation planned for 2026, the building is expected to reach 352 metres ahead of its planned Spring 2027 opening.

Interior fit-outs underway across 1,504 rooms and suites

All 1,530 guest accommodations have now reached full structural completion, with interior fit-outs underway across 1,504 rooms and suites. The tower’s structural concrete frame is complete, 79% of the façade has been installed, and the surrounding low-rise buildings have achieved 99% structural completion. With the main structure finished, the project has moved into the full interior build-out phase covering rooms, suites, enclave accommodations, food and beverage venues, and key public spaces.

Resort features planned across 60 hectares

Upon opening, Wynn Al Marjan Island will debut as the region’s first fully integrated resort. Spread across more than 60 hectares, the project will include 1,217 resort rooms and 297 Enclave suites, along with two Royal Apartments, four Garden Townhomes, and 10 Marina Estates. Planned facilities include 22 restaurants, lounges, and bars, a beach club, a spa and beauty destination, and a skylit shopping parterre. The resort will also feature Coral Court for celebrations and events, The Showroom theatre, 12 pools, a 420-metre white-sand beach, and a deep-water marina for superyachts.

Ceremony held atop the highest building in the Northern Emirates

To mark the topping out milestone, senior leaders from Wynn Resorts, Wynn Design & Development and Marjan gathered at the summit of the tower overlooking the Arabian Gulf. The ceremony recognised the completion of the tower structure, with guests receiving a commemorative steel bar from the building and participating in the pouring of the final concrete.

Leadership comments on the construction milestone

Max Tappeiner, President, Wynn Al Marjan Island, comments ‘Standing at 352m and, as the highest building in the Northern Emirates, Wynn Al Marjan Island is reshaping the skyline of Ras Al Khaimah and anchors a destination designed for guests who expect the very best. Reaching the tower’s highest structural concrete point in just over two years is more than a construction achievement; it is a defining moment for Wynn Resorts and a powerful testament to the talent and dedication of the teams bringing this vision to life.’

Abdulla Al Abdouli, Group CEO, Marjan, comments, “Wynn Al Marjan Island is more than a single development; it is the centrepiece of a new global destination taking shape in Ras Al Khaimah. Reaching this construction milestone brings us closer to welcoming the world to a resort that will redefine the Emirate’s hospitality offering and elevate Al Marjan Island and Ras Al Khaimah as a must-visit destination. Together with Wynn Resorts, we are creating a destination that blends iconic design, exceptional experiences and enduring value for residents, tourists and the wider tourism economy.”

Barry Lewis, CEO at ALEC Holdings said, “We congratulate Wynn on this major achievement and are proud to be their partner on a project that continues to redefine what is possible in regional construction. Their willingness to embrace the latest advancements in building technologies has enabled us to streamline workflows, elevate quality and maintain precision across every component of this landmark development. As we move into the next phase, our teams remain fully committed to delivering a world-class destination that stands out in every regard.”

Key construction milestones achieved

Key construction milestones to date include:

  • 100% of hotel room interior fit-out underway
  • 100% of the tower’s structural concrete completed
  • 100% of the guest accommodation structure completed
  • 99% of low-rise concrete and 96.5% steel structures completed
  • 90% of low-rise venue interior partitions and first & second-fix MEP commenced
  • 79% of tower façade panels installed (20,744 of 26,247)
  • 40% of low-rise exterior façades enclosed
  • 438,968 cubic meters of concrete poured
  • 18,000+ construction jobs created

Second joint-venture project: Janu Al Marjan Island

Alongside this progress, Wynn Resorts and Marjan are also moving ahead with a second joint-venture project on Al Marjan Island, Janu Al Marjan Island, announced in November 2025 and currently under construction. The development will bring Aman Group’s sister brand, Janu, to Ras Al Khaimah, with an opening planned for late 2028. Together, the two projects cover more than 60 acres earmarked for future growth.